Tuesday, May 16, 2006
Hello everybody. In the last post we had just started to make the fuselage skeleton. Well the skeleton is now finished and with all the um and ar procastinating ect I was surprised that we had only just hit the 200 hour mark. As you can see we have now turned the fuselage over and we are getting ready to start skinning the bottom but before we can do this we have to get the skeleton straight and level again
We have put the bottom skin on followed by the lower sidewall skins and from then on the rest is pretty well self explanatory. Total time to this point 218 hours.
The undercarriage channel and centre floor are now in place and we have had a little bit of help from the youngest member of the team Henry.