Monday, June 05, 2006


The next part to do is the rear side walls this took around 6 hours a side after that luggage compartment rear wall.

The rear wall took 3 hours to do. From here it is onto the centre side walls.

Here we have one sidewall clecoed on and the other is ready too be marked out and drilled. Total time to this point is 272 hours.
until next time cheers.

Sunday, June 04, 2006

Gday everybody well it still has not rained. So we have been building again and as you will see it is all starting to come together nicely

We have finished putting the bottom skins on and turned the airframe back over total time is 237 hours.

The next step was to make the bellcrank for the elevator pushrod and set the assembly up and run the rudder cables. This took 10 hours. So total time is 247 hours.